The following checklist reflects Skylight Lending comprehensive internal review process for M1s.

All criteria must be met to qualify for M1, and these requirements are consistent throughout our entire ecosystem.

Portal Qualifying (PQ)

Item:

Criteria that will be reviewed

Account Details

  • Name, address, kW size matches planset & production model

Contract Details

  • Production kWh & system size within tolerance (PPA vs Lease)

  • (I/A) Battery tab match what was installed

  • (I/A) Adders match what was installed

Portal Qualifying

 


Operational

Item:

Criteria that will be reviewed

Monitoring Portal Site Identifier (Optional for M2, though suggested for initial review)

  • Inverter (and battery I/A) monitoring site ID is supplied. 
  • Site access is granted (site owner designation not advised until M3).
  • Current Transformers (CTs) are installed correctly according to manufacturer specifications. 
  • Cell kits and Revenue Grade Metering (RGM) are mandatory for all projects. If the equipment is installed indoors and signal strength is weak, a cellular signal booster may be necessary. In areas where cellular service is unavailable, a wireless gateway or ethernet connection is required for remote monitoring (though this is rare).

Regulatory approvals

Incentives (I/A)

  • Documents submitted for applicable states 

 

Design Package Files

Item:

Criteria that will be reviewed

Planset

  • System size & module count match vs what was installed on site
  • Module manufacturer & wattage match what was installed on site
  • Inverter, racking, & all other components match what was installed on site
  • Planset is accurate (within tolerance) vs what was installed on site (Tilt, azimuth, etc)

Production Model

  • Approved platform is used (No mixing or matching of components). 
  • Correct inputs and system loss settings are applied (including snow loss by state, shading, etc.).
  • Design on the production model is accurate (within acceptable limits) compared to the actual installation on-site.

Shade Report

  • Design on the shade report is accurate (within tolerance) vs what was installed on site

 

Photo Documentation of Installation

Item:

Criteria that will be reviewed

Project Site

Roofing

Electrical Requirements

  • Photo Documentation Requirements
  • Electrical conditions qualify and electrical work follows Skylight Lending best practices
  • (I/A) Tesla MCI Requirements executed

(I/A) Storage

Commissioning Process

 

Requirements for Approval

All requirements must be met to achieve M2. While these requirements are consistent across our ecosystem, the QC technician reviewing the submission may, at their discretion, grant conditional approvals. Conditional approvals are M2 approvals that allow some flexibility, permitting certain missing or incomplete items to be submitted at M3. Conditional approvals are automatically granted when possible – Skylight Lending does not grant exceptions upon request.

Possible scenarios for Conditional approval consideration: Minor missing uploads or basic installation issues resolved with a site visit.

Scenarios that will not qualify for Conditional approval: Code violations, violations of manufacturer specifications, significant workmanship issues, high error rates in submissions, etc.